Understanding Welding Cost Estimation: A Practical Guide
Estimating welding costs is an essential skill for fabricators, estimators, and project managers alike. A well-structured estimate supports profitability, efficient resource use, and competitive bidding.
This guide walks you through the main cost elements, a practical step-by-step procedure, and includes key formulas, symbols, and worked examples with final numbers so you can see exactly how it all fits together. An article version can be found here.
Why Welding Cost Estimation Matters
If you donโt know your real welding cost per weld length, you risk:
Underquoting and losing money
Overquoting and losing bids
Missing hidden costs like power and real labour overhead
The Four Main Costs
Every weld cost breaks down into:
Labour (wages + benefits + shop overhead)
Power (electricity used by the welding machine)
Consumables (electrodes, filler wire, shielding gas)
(Base Material โ not covered here, but consider it for full jobs)
In simple terms:
Total Welding Cost = Labour Costs + Consumable Costs + Power Costs + Base Material Costs
How to Build a Realistic Labour Rate
A welderโs shop cost is not just the hourly wage.
Example:
Hourly wage: $35/hr
Employer-paid payroll costs (CPP/EI/WSIB): $4/hr
Vacation pay (4%): $1.40/hr
Health & dental benefits: $3/hr
Shop overhead (heat, lights, supervision, admin): $12/hr
Total: $55โ$60/hr real cost
Use your actual numbers โ your accountant or payroll team can help.
Key Concept: Operating Factor
Welders arenโt welding 100% of the time.
Typical Arc-On time: 20โ40%
The rest is setup, moving parts, waiting, or repositioning.
This ratio is called the Operating Factor (OF):
OF = (Arc Time / Total Shift Time)
A higher OF means better use of labour and equipment.
How to Get Good Numbers
Deposition rate โ Get from your welding procedure spec (WPS) or electrode datasheet. (E.g., SMAW: 6โ10 lb/hr)
Machine power draw โ Use typical amps ร volts, then adjust for efficiency.
Hydro rate โ Check your latest BC Hydro bill (e.g., $0.1408/kWh).
Worked Example # 1
Scenario: Youโre welding a fillet-joint using a Lincoln CRX10ia Cobot Welder, RapidArc ArMix GMAW process using R450 PowerWave.
Fillet Joint
Key data:
Wire Feed Speed ๐ท = 200๐๐.๐๐๐โ1
Travel Speed ๐ท = 18๐๐.๐๐๐โ1
Deposition efficiency ๐๐ = 0.96
Wire (ER70S-6) Cost ๐ถ๐ค๐๐๐ = $3.64 ๐๐โ1
Wire linear density ๐ = 2200๐๐.๐๐โ1
Labour rate (incl. overhead) ๐ถhr = $39.20 โโ1
Operating factor OF โ 0.30
Gas Flowrate 55๐๐ก3.โ๐โ1
Gas Cost ๐ถ๐๐๐ = 4.73$.๐๐กโ3
Arc voltage โ 21.4 V (from PowerWave R450 readings)
Amperage โ 157 A (from PowerWave R450 readings)
Weld Length ๐ฟ = 5.11๐๐ (measured after welding-can also just
be length of piece)
BC Hydro rate: $0.1408/kWh
Power efficiency โ 0.85
Power factor โ 0.8
Updated labour cost: $39.20/hr (incl. vacation, benefits)
Fillet Joint Scan Before and After Weld
Step 1: Calculate Weld Area
To calculate the weld area, we typically start with either the specified fillet size or the actual weld geometry. In most workshop settings, inspectors or welders use simple measurement tools, or they estimate the area based on the target fillet size.
For our example, weโll refer to the dimensions shown in Figure above. Since fillet welds form roughly triangular cross-sections, we can approximate the weld area as that of a right triangle. However, to account for over-weldingโwhich is common in practiceโwe add an additional 15% to the calculated area.
Note: 5 mm โ 0.2 in.
Equation for Weld Area
Aw (Weld Cross-sectional Area) = Atriangle + Aoverfill
Aw = Atriangleร(1+0.15) = (1/2 ร 0.2 ร 0.2)ร(1+ 0.15)
Aw = 0.02 + 0.003 = 0.023 in2
Note: You can use SKC weld area calculator to save time.
Step 2: Volume and Weight
To estimate the weight of the deposited weld metal, we begin by calculating its volume. This is done by multiplying the cross-sectional area of the weld by the length of the weld bead. Once we have the volume, we multiply it by the density of the filler metal to determine the total weight.
Equation for Volume
The volume of weld metal deposited is given by:
V = Aw ร L = 0.023 in2 ร 5.11 in = 0.11753 in3
Equation for Weight
Multiplying the volume by the density gives us the weight:
W = V ร ฯ = 0.11753 in3 ร 0.283 lb/in3 = 0.0333 lb
Parameter Definitions
Aw: Cross-sectional area of the weld bead (inยฒ)
L: Length of the weld (in)
V: Volume of weld metal deposited (inยณ)
ฯ: Density of the filler metal (lb/inยณ), typically 0.283 for steel
W: Weight of deposited weld metal (lb)
Step 3: Estimating Arc Time
Arc time is the amount of time the welding arc remains active. This is important for calculating labor, power consumption, and overall process efficiency.
Step 3.1 โ Calculate Weight of Wire Consumed
The weight of consumed wire depends on how much of it is actually deposited during welding. This is where the deposition efficiency comes in:
Wwire = Wweld / ฮทd = 0.0333 lb / 0.96 = 0.03197 lb
Where:
- Wweld = Weight of deposited weld metal (lb), from Step 2
- ฮทd = Deposition efficiency (typically 0.96 for GMAW)
Step 3.2 โ Calculate Length of Consumed Wire
The length of wire consumed is calculated using the linear density of the wire and the weight of wire consumed:
Lwc = ฮปwire ร Wwire = 2200 in/lb ร 0.03197 lb = 70.33 in
Where:
- ฮปwire = Linear density of the filler wire (in/lb)
- Wwire = Weight of wire consumed (lb)
Step 3.3 โ Calculate Arc Time from Wire Consumption
Arc time can be determined by dividing the length of welding wire consumed by the wire feed speed:
Tarc = Lwc / WFS = 70.33 in / 200 in/min = 0.352 min โ 21.1 s
Where:
Tarc = Arc time (minutes or seconds)
Lwc = Length of wire consumed (inches)
WFS = Wire Feed Speed (in/min)
Step 4: Estimating Weld Consumables
In this step, we account for two primary consumables in the welding process: filler wire and shielding gas.
The weight of wire consumed (Wwire) was already calculated in Step 3:
Wwire = 0.03197 lb
Now, we calculate the volume of shielding gas used during welding. This depends on the arc time and the gas flow rate.
Shielding Gas Consumption
The formula for shielding gas consumption is:
Gc = (Tarc ร Gflow) / 60
Gc = (0.352 min ร 55 ft3/hr) / 60 = 0.323 ft3
Where:
- Gc = Total shielding gas consumed (ftยณ)
- Tarc = Arc time in minutes (from Step 3)
- Gflow = Gas flow rate in ftยณ/hr
This gives us an estimate of how much shielding gas (typically Argon or a gas mix) is used during the weld. While the amount may seem small for a short weld, it adds up over longer production runs and should be included in cost estimates.
Step 5: Estimating Power Cost
Power cost is a small but important part of the total welding cost. Itโs based on the electrical energy consumed during the weld, which depends on the arc power, equipment efficiency, power factor, and arc time.
Step 5.1 โ Calculate Arc Power
Parc = V ร I = 21.4 V ร 157 A = 3.36 kW Where:
- V = Arc voltage (volts)
- I = Arc current (amperes)
- Parc = Power delivered to the arc (kW)
Step 5.2 โ Adjust for System Efficiency
Pinput = Parc / ฮทeff = 3.36 kW / 0.85 = 3.91 kW
Where:
- ฮทeff = System efficiency (dimensionless)
- Pinput = Power drawn by the welding machine (kW)
Step 5.3 โ Account for Power Factor
Preal = Pinput ร PF = 3.91 kW ร 0.8 = 3.128 kW
Where:
- PF = Power factor (dimensionless)
- Preal = Actual power drawn from the grid (kW)
Step 5.4 โ Calculate Energy Used
Arc time from Step 3 is 0.352 min, or 0.00587 hr:
EkWh = Preal ร t = 3.128 kW ร (0.352 / 60) hr = 0.01835 kWh
Step 5.5 โ Compute Power Cost
Power Cost = EkWh ร CkWh = 0.01835 kWh ร $0.1408/kWh = $0.0026
Even though the power cost is quite lowโjust a fraction of a centโthis estimate only includes the energy consumed during welding. Additional power usage by robots, controls, and idle systems is not accounted for here, meaning the actual cost could be slightly higher in real-world scenarios.
Step 6: Final Cost Breakdown
To determine the total welding cost, we sum the three key components:
Labour Cost
Consumables Cost
Power Cost
Labour Cost
Labour cost is based on the arc time and hourly labour rate:
Labour = Tarc ร Chr = (0.352 / 60) hr ร $39.20/hr = $0.229
Where:
- Tarc = Arc time in minutes
- Chr = Labour rate ($/hr)
Consumables Cost
This includes the cost of shielding gas and filler wire:
Consumables = Gc ร Cg + Wwire ร Cwire
= 0.323 ftยณ ร $4.73/ftยณ + 0.03197 lb ร $3.64/lb
= $1.644
Where:
- Gc = Volume of shielding gas consumed (ftยณ)
- Cg = Cost per cubic foot of gas
- Wwire = Weight of welding wire used (lb)
- Cwire = Cost per pound of wire
Power Cost
Previously calculated in Step 5:
Power = $0.0026
Total Welding Cost
Summing all components:
Total Cost = $0.229 (Labour) + $1.644 (Consumables) + $0.0026 (Power) = $1.8756
This final cost represents the direct welding cost for this short segment. Itโs ideal for budgeting, quoting, and evaluating efficiency in a production setting.
Worked Example # 2
Scenario: Youโre welding a flange on a beam-column connection as shown in the figure below.
Image Source: The Procedure Handbook of Arc Welding, Estimating Welding Costs
Key data:
Plate thickness: 1 ยพ in
Bevel angle: 45ยฐ
Root spacing: ยผ in
Reinforcement: โ in (per AWS limit)
Electrode: E7027, 3/16 in, 280 A (AC)
Deposition rate: 7.8 lb/hr
Deposition efficiency: 66%
Electrode price: $0.35/lb
Updated labour cost: $39.20/hr (incl. vacation, benefits)
Operating Factor: 0.30
Power source: Lincoln R450 Power Wave
Welding voltage: ~32 V
Power factor: 0.8
Hydro rate: $0.1408/kWh
Weld length: 14 in
Weld metal density: 0.283 lb/inยณ
Step 1: Calculate Weld Area
The weld Area can be calculated by splitting the area in figure 1 into 3 sections, โArea 1โ is obtained using formula for rectangle, โArea 2โ is obtained using formula for triangle, and โArea 3โ is obtained using formula for parabola.
Aw (Weld Cross-sectional area) = Area1 + Area2 + Area3
Aw = rt + (t2 / 2) + (2 / 3) a (r + t)
Aw = (0.25 ร 1.75) + (1.752 / 2) + (2 / 3) ร 0.375 ร (0.25 + 1.75) = 2.47 in2
Step 2: Calculate Volume, then Weight of Weld
V (Volume of Weld) = Aw (Weld Cross-sectional area) ร L (Length of weld)
V = Aw ร L = 2.47 in2 ร 14 in = 34.6 in3
W (Weight of Weld) = V (Volume of Weld) * ฯ(density of weld metal)
W = V ร ฯ = 34.6 in3 ร 0.283 lb/in3 = 9.62 lb
Step 3: Arc-Time Requirement
Tarc (Arc Time) = Weight of Weld / (D (Deposition rate) ร OF (Operating Factor) )
Tarc = W / (D ร OF) = 9.62 / (7.8 ร 0.30) = 4.11 hr
Step 4: Electrode Consumption
We (Weight of Electrode Consumed) = W(Weight of Weld metal) / ฮทd (deposition efficiency)
We = W / ฮทd = 9.62 / 0.66 = 14.6 lb
Step 5: Power Costs
Parc (Arc Power) = V (Welding Voltage) ร A (Welding Amperage)
Parc = 32 V ร 280 A = 8.96 kW
Pinput (Input Power) = Parc (Arc Power) / Machine Efficiency
Pinput = 8.96 / 0.85 = 10.54 kW
Preal = Pinput (Input Power) ร Power Factor
Preal = 10.54 kW ร 0.8 = 8.43 kW
EkWh (Total Power consumed) = Preal (Consumed Power) ร ArcTime
EkWh = 8.43 kW ร 4.11 hr = 34.65 kWh
Power Cost = EkWh (Total Power consumed) x BC-Hydro Power Cost
Power Cost = 34.65 kWh ร $0.1408/kWh = $4.88
Final Costs:
Labour Cost = 4.11 hr ร $39.20/hr = $161.31
Electrode Cost = 14.6 lb ร $0.35/lb = $5.11
Power Cost = $4.88
Total Welding Cost = $161.31 + $5.11 + $4.88 = $171.30
Final Key Points
Use real wage + benefits + overhead.
Include realistic arc time โ most shops are ~30% efficient for manual work.
Donโt forget power, even for small jobs.
Use SKC weld area calculator if needed.